Question: Please answer with detail working and explaination clearly During a recent month, Charlotte Company planned to provide cleaning services to 30 customers for $27 per
Please answer with detail working and explaination clearly

During a recent month, Charlotte Company planned to provide cleaning services to 30 customers for $27 per hour. Each job was expected to take 4.0 hours. The company actually served 20 more customers than expected, but the average time spent on each job was only 3.5 hours each. Charlotte's revenues for the month were O A. $1,485 more than expected. O B. $1,485 less than expected. O C. $2, 160 more than expected. O D. Cannot be determined from data given