Question: Please answer with detailed explanation else downvote. Item LS: MULT 30 Gross Requirements Scheduled Receipts Projected on Hand Net requirements Planned Order Receipts Planned Order

Please answer with detailed explanation else downvote.

Item LS: MULT 30 Gross Requirements Scheduled Receipts Projected on Hand Net requirements Planned Order Receipts Planned Order Releases 2 Period 100 80 2 30 60 3 50 4 50 5 60 13. What are the net requirements for Item B in period 3? 14. What is the planned order release for Item B in period 2? 15. What is the projected on hand for Item B in period 4? 16. What is the planned order receipt for Item B in period 5?