Question 12 Consider the following data regarding a shop order that was just released Lotste 100 pieces Due Date 20 days from now (each day is 8 hours) Routing Operation Work Center Setup time Runtime/piece 1 100 3 hrs 2 200 5 hrs 2 hrs 3 300 9 hrs 3 hrs How many hours of move and queue time is built into the manufacturing lead time for this part? | 0 A A E1 | # # E = 11. 12pt Paragraph