Question: PLEASE ASAP Bonus Question (6 bonus points possible) Layt Clock Company has developed the following flexible budget for its overhead costs. The standard hours allowed
PLEASE ASAP

Bonus Question (6 bonus points possible) Layt Clock Company has developed the following flexible budget for its overhead costs. The standard hours allowed per unit is 1.2 hours. Manufacturing overhead at Layt is applied to production on the basis of standard machine-hours: Budget Information Machine Hours 26,400 Clocks produced............ 22,000 Variable overhead cost per machine hour (standard) ... $5.90 Fixed overhead cost per unit per machine hours (standard) $6.48 Total Fixed overhead cost..... $171,072 The actual results for the year were as follows: Number of clocks produced .......... 21,500 Machine-hours incurred ............. 24,940 Variable overhead cost... $145,899 Fixed overhead cost $170,540 Required: 1. Compute Variable Overhead Rate Variance. 2. Compute Variable Overhead Efficiency Variance. 3. Compute Fixed Overhead Budget Variance. 4. Compute Fixed Overhead Volume Variance
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts