Question: please assist #9 9. Construct a Gantt chart for the following: Activity Predecessor Activity 1 2 3 4 Time (Weeks) 3 6 3 5 1
9. Construct a Gantt chart for the following: Activity Predecessor Activity 1 2 3 4 Time (Weeks) 3 6 3 5 1 2 ow al COMPLETE GANTT CHART (3 POINTS) 1 2 3 4 6 7 8 9 10 11 12 13 14 15 2 3 4 COMPLETE THE CPM/PERT DIAGRAM BELOW & Calculate Slack (4 POINTS), Highlight the critical path (1 POINT) # ES EF # ES EF 1 -> Time LS LF Time LS LF FINISH # ES EF # ES EF - Time LS LF Time LS LF
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
