Question: PLEASE BE SURE TO CONSTRUCT AN AON DIAGRAM. NOT A AOA 27. Given the following activities required for staging a community play on Independence Day,

PLEASE BE SURE TO CONSTRUCT AN AON DIAGRAM. NOT A AOA
27. Given the following activities required for staging a community play on Independence Day, a. Construct an AON diagram. b. Determine the earliest expected completion time for the play. c. Based on the path with the longest expected duration, what completion date are you 80 percent confident of achieving? 40 percent confident? d. Will a l-day delay in this project be serious? Time (days) Activity Predecessor a m b 2 - 2 1 1 4 5 7 3 8 3,6 9 4 5 7 8 139,10 14 7 15 1 2,13 2 5 3 7 11 5 9 5 7 3 15 6 7 12 16 4 5 5 10 12 6 10 7 9 3 17 8 8 14 17 6 5 7 13 13 7 11 9 11 3 19 10 15 16 18Step by Step Solution