Question: Please check for accuracy and assist with final question. Please show work. The Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration


Please check for accuracy and assist with final question. Please show work.
The Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of vintage Porsche automobiles. One of Jensen's regular customers asked him to prepare an estimate for the restoration of a 1964 model 356SC Porsche. To estimate the time and cost to perform such a restoration, Jensen broke the restoration process into four separate activities: disassembly and initial preparation work (A), body restoration (B), engine restoration (C), and final assembly (D). activity A has been completed, activities B and C can be performed independently of each other; however, activity D can be started only if both activities B and C have been completed. Based on his inspection of the car, Jensen believes tha following time estimates (in days) are applicable: Activity Optimistic Most Probable Pessimistic A 3 4 8 B 2.5 4 5.5 5 8 11 D 2 4 12 Jensen estimates that the parts needed to restore the body will cost $4000 and that the parts needed to restore the engine will cost $5000. His current labor costs are $500 a day. a. Which project network is correct? (0) (ii) B Start Finish Start Finish (iv) Start Finish Start Finish Network (iii) b. What is the expected project completion time? Critical Path: A-B-D If required, round your answer to one decimal place. Expected time = 10.24 days C. Jensen's business philosophy is based on making decisions using a best- and worst-case scenario. Develop cost estimates for completing the restoration based on both a best- and worst-case analysis. Assume that the total restoration cost is the sum of the labor cost plus the material cost. If required, round non-monetary answers to the nearest whole number. If required, round monetary answers to the nearest dollar. Best Case (Optimistic Times) = 12 days Total Cost = $ 15,000 Worst Case (Pessimistic Times) = 25.5 days Total Cost = $ 21,750 d. If Jensen obtains the job with a bid that is based on the costs associated with an expected completion time, what is the probability that he will lose money on the job? If required, round your answer to the nearest dollar. Bid Cost = $ 14,120 If required, round your answer to two decimal places. The probability is 0.50 e. If Jensen obtains the job based on a bid of $19,500, what is the probability that he will lose money on the job? Note: Use Appendix B to identify the areas for the standard normal distribution. If required, round your answer to four decimal places. The probability of a loss isStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
