Question: Please choose the correct answerfor the below multiple choice questions: 1 . In competitive bid contracts which type of bond that the owner requests from

Please choose the correct answerfor the below multiple choice questions:
1. In competitive bid contracts which type of bond that the owner requests from the contractor to protect him against any leans to project
a- None of the bonds mentioned
b- Performance bond
c- bid bond
d- Labor and material bond
e- lean bond
2. In some projects prior the award of contract the owner is forced to issue a letter of intent to the lowest responsible bidder why?
a- When there are changes to the design documents
b- None of the answers
c- The owner wants to select this contractor no matter what
d- When there is a problem in the prequalification document
e- When there is an error in the submitted bid that must be corrected
3. In ancient times master builders did construction of projects. In today times the closest delivery system to master/builder concept is
a- DBB
b- DB
c- CM at risk
d- Cost plus fee
e- CM
4. When a contractor submits a change order to the owner the following are options that the owner can make, which?
a- Accept and negotiate CO
b- Negotiate CO
c- Accept and reject CO
d- Reject CO
e- Determine the price of requested changes
5. The document that is not included in the bid package that the owner provides to the contractor:
a- General conditions
b- ADENDA
c- Plans and specifications
d- Bid form
e- Supplementary conditions
6. How many cost estimates that the owner receives throughout the project development process?
a-5
b-1
c-2
d-4
e-3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!