Question: please complete all parts to question 1. The project below currently has a total cost of $9,000, with direct costs currently at $6,300 and indirect

1. The project below currently has a total cost of $9,000, with direct costs currently at $6,300 and indirect costs currently $2,700. 1. Draw the network diagram and identify the critical path 2. Calculate the normal, least-cost and crash duration for the project below. 3. Calculate the cost associated with each duration, 4. Indirect cost overhead) is $200 per day. PATH Days Cyci Cyc2 Cyc3 Cyc4 Cyc5 Cyc7 Cyc8 Cyc? Cyc10 1 1. The project below currently has a total cost of $9,000, with direct costs currently at $6,300 and indirect costs currently $2,700. 1. Draw the network diagram and identify the critical path 2. Calculate the normal, least-cost and crash duration for the project below. 3. Calculate the cost associated with each duration, 4. Indirect cost overhead) is $200 per day. PATH Days Cyci Cyc2 Cyc3 Cyc4 Cyc5 Cyc7 Cyc8 Cyc? Cyc10 1
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
