Question: Please complete the ES, EF, LS, LF, and slack for the project below. Activity Description Duration (weeks) Immediate predecessors ES EF LS LF Slack A

Please complete the ES, EF, LS, LF, and slack for the project below.

Activity Description Duration (weeks) Immediate predecessors ES EF LS LF Slack
A Contract negotiation with selected vendors 3 -
B Decide on the best data extraction platform and begin software coding 5 C
C Contract negotiation with package and label manufacturers 2 -
D Screen and hire transportation personnel 3 -
E Market logistic arrangements 1 A
F Organize advertising brochures and campaign print ads 4 D
G Logistical arrangements for sales representatives 1 E
H Target market final arrangements 3 C, D
I Finish the final production process 5 F, H
J Hire additional sales staff, and make sales demonstration arrangements 4 E, B, H
K Distribute media advertising packages and arrange for commercial distribution 5 G
L Arrange sales tracking and monitoring 2 F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!