Question: Please complete the ES, EF, LS, LF, and slack for the project below. Activity Description Duration (weeks) Immediate predecessors ES EF LS LF Slack A
Please complete the ES, EF, LS, LF, and slack for the project below.
| Activity | Description | Duration (weeks) | Immediate predecessors | ES | EF | LS | LF | Slack |
| A | Contract negotiation with selected vendors | 3 | - | |||||
| B | Decide on the best data extraction platform and begin software coding | 5 | C | |||||
| C | Contract negotiation with package and label manufacturers | 2 | - | |||||
| D | Screen and hire transportation personnel | 3 | - | |||||
| E | Market logistic arrangements | 1 | A | |||||
| F | Organize advertising brochures and campaign print ads | 4 | D | |||||
| G | Logistical arrangements for sales representatives | 1 | E | |||||
| H | Target market final arrangements | 3 | C, D | |||||
| I | Finish the final production process | 5 | F, H | |||||
| J | Hire additional sales staff, and make sales demonstration arrangements | 4 | E, B, H | |||||
| K | Distribute media advertising packages and arrange for commercial distribution | 5 | G | |||||
| L | Arrange sales tracking and monitoring | 2 | F |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock