Question: Please complete the following Individual Assignment on Critical Path Analysis Assignment 3. Table of a Network diagarm, need to draw the out the diagram. Activity
Please complete the following Individual Assignment on Critical Path Analysis Assignment 3.
Table of a Network diagarm, need to draw the out the diagram.
Activity Preceding Activities Durations in Day s
Start - 0
A Start 2
B A 3
C B 4
D B 3
E C,D 3
Finish E 0
Prepare the network diagram, what is the Critical path, calculate forward pass slack on activity D and backward pass.