What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?

Activity Normal Time (DAYS) Crash Time (DAYS) Normal Cost Crash Cost Immediate Precedecessor(S)
A 6 5 $900 $1,000
B 8 6 300 400
C 4 3 500 600
D 5 3 900 1,200 A
E 8 5 1,000 1,600 C