Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes.

a. Calculate the theoretical minimum number of workstations?

b. Balance this line using the longest task time heuristic.

c. What tasks are assigned to which stations? Does the solution have the minimum number of stations? Explain.

d. How much idle time is there, summed over all workstations?

e.What is the efficiency of this line?

Work Task Tast Time (seconds) Task Predecessor(s)
A 70 -
B 60 A
C 120 B
D 60 -
E 240 C, D
F 100 A
G 190 E, F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!