Question: please correct this problem Brief Exercise 6-35 (Algo) Long-term contract; revenue recognition upon completion (LO6-9) A construction company entered into a fixed price contract to
Brief Exercise 6-35 (Algo) Long-term contract; revenue recognition upon completion (LO6-9) A construction company entered into a fixed price contract to build an office building for $48 million. Construction costs incurred during the first year were $18 million and estimated costs to complete at the end of the year were $27 million. The building was completed during the second year. Construction costs incurred during the second year were $28 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue upon contract completion? (Enter your answers in whole dollars. Leave no cells blank.be certain to enter "0" wherever required.) Year 1 Year 2 Revenue
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts