Question: Please could you explain me step by step, I would appreciate it . ( 2 0 ) . Chapter 1 0 - Monitoring and Information

Please could you explain me step by step, I would appreciate it.(20). Chapter 10-Monitoring and Information Systems 6. A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of \(\$ 735,000\) for this point in time, but the actual cost is only \(\$ 550,000\). Based on this information,