Question: PLEASE CREATE A NET REQUIREMENTS PLAN AND SHOW YOUR WORK I HAVE POSTED THIS QUESTION A COUPLE TIMES AND NOBODY HAS MADE A NET REQUIREMENTS

PLEASE CREATE A NET REQUIREMENTS PLAN AND SHOW YOUR WORK I HAVE POSTED THIS QUESTION A COUPLE TIMES AND NOBODY HAS MADE A NET REQUIREMENTS PLAN FOR IT. THANK YOU
14.5 The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V,2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V,3 weeks to make W, 1 week to make X,2 weeks to make Y, and 1 week to make Z. Construct a net material requirements plan using the following on-hand inventoryStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts