Question: Please Create a Project Network showing ES, LS, EF, and LF and determine the slack for every activity in one Network. Table: Activity list of

Please Create a Project Network showing ES, LS, EF, and LF and determine the slack for every activity in one Network.
Table: Activity list of Reliable Construction project. Immediate Predecessors Estimated Duration Activity TUO cou A B D E F G H 1 Activity Description Excavate Lay the foundation Put up the rough wall Put up the roof Install the exterior plumbing Install the interior plumbing Put up the exterior siding Do the exterior painting Do the electrical work Put up the wallboard Install the flooring Do the interior painting Install the exterior fixtures Install the interior fixtures E D E, G F 1 2 weeks 4 weeks 10 weeks 6 weeks 4 weeks 5 weeks 7 weeks 9 weeks 7 weeks 8 weeks 4 weeks 5 weeks 2 weeks 6 weeks K L M N H K, LStep by Step Solution