Question: . Please design a work break down structure for a project with the requirements: Project Title: TAMU-C Monorail System Structure: Steel-frame rail system with concrete

.

Please design a work break down structure for a project with the requirements:

Project Title: TAMU-C Monorail System Structure: Steel-frame rail system with concrete piers as required to support monorail cars with minimum capacity of 30 people per monorail car.

Location/Orientation: Each contractor is to provide a campus map with layout of monorail train station locations and presenting a proposed monorail route. At a minimum, the monorail should have stations at Whitley Hall, What-a-Burger, the McDowell Administration building, Memorial Stadium, and the RSC. Additional stations may be proposed to ensure adequate travel support for students and visitors. Train stations: Stations should include covered entry and exits to shield travelers from the elements.

Time Frame: Physical construction may commence on June 1 and must be completed within 12 months.

That also has a schedule as follows.

---------------------------------------------------------------------------------------------------------------------------------------

| Task | Duration | Start Date | End Date | Dependencies | Resources |

---------------------------------------------------------------------------------------------------------------------------------------

| 1. Project Initiation | 5 days | 01-Jun-23 | 07-Jun-23 | | Project Manager |

---------------------------------------------------------------------------------------------------------------------------------------

| 2. Campus Mapping | 10 days | 08-Jun-23 | 21-Jun-23 | | Surveyor |

---------------------------------------------------------------------------------------------------------------------------------------

| 3. Route Planning | 15 days | 22-Jun-23 | 12-Jul-23 | 2. Campus Mapping | Route Planner |

---------------------------------------------------------------------------------------------------------------------------------------

| 4. Station Design | 10 days | 13-Jul-23 | 24-Jul-23 | 2. Campus Mapping | Architect |

---------------------------------------------------------------------------------------------------------------------------------------

| 5. Procurement | 15 days | 25-Jul-23 | 14-Aug-23 | 4. Station Design | Procurement Team |

---------------------------------------------------------------------------------------------------------------------------------------

| 6. Foundation | 30 days | 15-Aug-23 | 23-Sep-23 | 5. Procurement | Construction Team |

---------------------------------------------------------------------------------------------------------------------------------------

| 7. Steel-frame | 45 days | 24-Sep-23 | 08-Nov-23 | 6. Foundation | Construction Team |

| construction |

---------------------------------------------------------------------------------------------------------------------------------------

| 8. Monorail Car | 60 days | 09-Nov-23 | 07-Jan-24 | 7. Steel-frame construction | Manufacturing Team|

| Manufacturing |

---------------------------------------------------------------------------------------------------------------------------------------

| 9. Monorail Car | 30 days | 08-Jan-24 | 07-Feb-24 | 8. Monorail Car Manufacturing | Assembly Team |

| Assembly |

---------------------------------------------------------------------------------------------------------------------------------------

| 10. Monorail System | 45 days | 08-Feb-24 | 26-Mar-24 | 9. Monorail Car Assembly | Installation Team |

| Installation |

---------------------------------------------------------------------------------------------------------------------------------------

| 11. Testing & | 15 days | 27-Mar-24 | 12-Apr-24 | 10. Monorail System Installation | Testing Team |

| Commissioning |

---------------------------------------------------------------------------------------------------------------------------------------

| 12. Final Touches | 10 days | 13-Apr-24 | 24-Apr-24 | 11. Testing & Commissioning | Construction Team |

---------------------------------------------------------------------------------------------------------------------------------------

| 13. Project Closure | 5 days | 25-Apr-24 | 01-May-24 | 12. Final Touches | Project Manager |

---------------------------------------------------------------------------------------------------------------------------------------

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!