Question: . Please design a work break down structure for a project with the requirements: Project Title: TAMU-C Monorail System Structure: Steel-frame rail system with concrete
.
Please design a work break down structure for a project with the requirements:
Project Title: TAMU-C Monorail System Structure: Steel-frame rail system with concrete piers as required to support monorail cars with minimum capacity of 30 people per monorail car.
Location/Orientation: Each contractor is to provide a campus map with layout of monorail train station locations and presenting a proposed monorail route. At a minimum, the monorail should have stations at Whitley Hall, What-a-Burger, the McDowell Administration building, Memorial Stadium, and the RSC. Additional stations may be proposed to ensure adequate travel support for students and visitors. Train stations: Stations should include covered entry and exits to shield travelers from the elements.
Time Frame: Physical construction may commence on June 1 and must be completed within 12 months.
That also has a schedule as follows.
---------------------------------------------------------------------------------------------------------------------------------------
| Task | Duration | Start Date | End Date | Dependencies | Resources |
---------------------------------------------------------------------------------------------------------------------------------------
| 1. Project Initiation | 5 days | 01-Jun-23 | 07-Jun-23 | | Project Manager |
---------------------------------------------------------------------------------------------------------------------------------------
| 2. Campus Mapping | 10 days | 08-Jun-23 | 21-Jun-23 | | Surveyor |
---------------------------------------------------------------------------------------------------------------------------------------
| 3. Route Planning | 15 days | 22-Jun-23 | 12-Jul-23 | 2. Campus Mapping | Route Planner |
---------------------------------------------------------------------------------------------------------------------------------------
| 4. Station Design | 10 days | 13-Jul-23 | 24-Jul-23 | 2. Campus Mapping | Architect |
---------------------------------------------------------------------------------------------------------------------------------------
| 5. Procurement | 15 days | 25-Jul-23 | 14-Aug-23 | 4. Station Design | Procurement Team |
---------------------------------------------------------------------------------------------------------------------------------------
| 6. Foundation | 30 days | 15-Aug-23 | 23-Sep-23 | 5. Procurement | Construction Team |
---------------------------------------------------------------------------------------------------------------------------------------
| 7. Steel-frame | 45 days | 24-Sep-23 | 08-Nov-23 | 6. Foundation | Construction Team |
| construction |
---------------------------------------------------------------------------------------------------------------------------------------
| 8. Monorail Car | 60 days | 09-Nov-23 | 07-Jan-24 | 7. Steel-frame construction | Manufacturing Team|
| Manufacturing |
---------------------------------------------------------------------------------------------------------------------------------------
| 9. Monorail Car | 30 days | 08-Jan-24 | 07-Feb-24 | 8. Monorail Car Manufacturing | Assembly Team |
| Assembly |
---------------------------------------------------------------------------------------------------------------------------------------
| 10. Monorail System | 45 days | 08-Feb-24 | 26-Mar-24 | 9. Monorail Car Assembly | Installation Team |
| Installation |
---------------------------------------------------------------------------------------------------------------------------------------
| 11. Testing & | 15 days | 27-Mar-24 | 12-Apr-24 | 10. Monorail System Installation | Testing Team |
| Commissioning |
---------------------------------------------------------------------------------------------------------------------------------------
| 12. Final Touches | 10 days | 13-Apr-24 | 24-Apr-24 | 11. Testing & Commissioning | Construction Team |
---------------------------------------------------------------------------------------------------------------------------------------
| 13. Project Closure | 5 days | 25-Apr-24 | 01-May-24 | 12. Final Touches | Project Manager |
---------------------------------------------------------------------------------------------------------------------------------------