Question: Please do all. Indicate the BEST acronym provided below (choices can be used once, not at all, or multiple times additionally, some matching may not
Please do all. Indicate the BEST acronym provided below (choices can be used once, not at all, or multiple times additionally, some matching may not have an appropriate choice available.
A: PERT B: Mock-up C: Risk Register D: Top-Down E: Phase Gate
F: Waterfall G: SOW H: ABC I: MPS J: EV
K: QFD L: DoE M: FTA N: Contingency plan
Project Estimation technique used to supplement traditional predictions _____________
Project document describing total Project scope __________
Project method used to organize work into smaller manageable segments _________________
Project strategy used to develop a product and enter production __________
Project Meetings at the end of each project phase __________
Project analysis technique used to feed into the design and risk id process ___________
Project financial monitoring technique __________
Production Plan for the Project _________
Project scheduling tool showing activity duration, slack, and dependencies ___________
Project method of optimizing design and reducing variance through test _________
Project tool used to prioritize and quantify concerns _________