Question: PLEASE DO BY HAND ON PAPER AND MAKE IT LEGIBLE. IF YOU POST EXCEL SOLUTION I WILL NOT THUMBS UP Fowler Marketing Research must assign
PLEASE DO BY HAND ON PAPER AND MAKE IT LEGIBLE. IF YOU POST EXCEL SOLUTION I WILL NOT THUMBS UP
Fowler Marketing Research must assign three projects, each having approximately the same priority, to three project leaders, with differing experience and ability Management wants to minimize the total number of days required to complete all three projects. The estimated completion times (days) for the three leaders / projects are: Leader / Project Terry Carle McClymonds 1 10 9 6 2 15 18 14 3 9 5 3 Develop and solve an Excel assignment model that will minimize the total completion time for all three projects