Set. (C) A system of three tasks T1(4, 1) ; T2(6,1.5), T3(9,1) and T4(10,2) are scheduled using EDF. If sporadic jobs Si(ri,ei,d )= $1 (3, 1, 11); $2 (6, 2, 19); $3 (4, 1.5, 12) arrive. Which of the sporadic jobs can be accepted? (Show relevant calculations, partial schedules and specify the reasons for the decision made)