Question: (please do it in microsoft word document , take a pic of your work in MICROSOFT word and uploaded here. DO NOT TAKE A PIC

(please do it in microsoft word document , take a pic of your work in MICROSOFT word and uploaded here. DO NOT TAKE A PIC IN PAPER PLASE).

Bill Fennema, a president of Fennema Construction, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AOA network and answer the questions that follow.

Activity

Immediate Predecessor(s)

Time Estimates (in weeks)

Optimistic

Most likely

Pessimistic

A

-

4

8

10

B

A

2

8

24

C

A

8

12

16

D

A

4

6

10

E

B

1

2

3

F

E, C

6

8

20

G

E, C

2

3

4

H

F

2

2

2

I

F

6

6

6

J

D, G, H

4

6

12

K

I, J

2

2

3

a) What is the variance for activity H? b) What is the critical path for the project? c) What is the estimated time of the critical path? d) What is the probability that the project duration will not be less than 35 weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!