Question: Please do not copy the existing solution as I think its not complete and/or is wrong. 7.4 Antonio plc makes Product X, the standard costs
Please do not copy the existing solution as I think its not complete and/or is wrong.

7.4 Antonio plc makes Product X, the standard costs of which are: Sales revenue 31 Direct labour (1 hour) (11) (10) (3) Direct materials (1 kg) Fixed overheads Standard profit The budgeted output for March was 1,000 units of Product X; the actual output was 1,100 units, which was sold for 34,950. There were no inventories at the start or end of March. The actual production costs were: Direct labour (1,075 hours) Direct materials (1,170 kg) 12,210 11,630 3,200 Fixed overheads Required: Calculate the variances for March as fully as you are able from the available information and use them to reconcile the budgeted and actual profit figures
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
