Question: please do not post a reference to another question that can be similar. I need help with this question exactly A project to build a
please do not post a reference to another question that can be similar. I need help with this question exactly
A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 68% complete. The planners were expecting to be only54% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,429,000 and it was done for only $1,309,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,509,000 but was actually done for $9,009,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,509,000. To date, they have spent $5,009,000 on the superstructure Calculate the schedule variance, schedule performance Index, and cost performance Index for the project to date. (Round your "performance index" values to 3 decimal places.) 15 Schedule variance Schedule performance Index Cost performance index
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
