Q4. (05 points) The diagram below shows the activities on the nodes, and the table shows the normal time and crash time (in days) and cost for each activity. B Start D E Activity Normal Time Crash Time Cost per day to crash A 6 6 B 10 8 $100 c 5 4 $300 D 4 1 $700 E 9 7 $500 F 2 1 $650 a) Which activity should be crashed to reduce the project completion time by one day? b) Which activity should be crashed to reduce the project completion by 2 days