Question: please do this for Items T,U,V,W,X,Y,Z The demand for subassembly S is 100 units in week 7. Each unit of requires 2 units of T

please do this for Items T,U,V,W,X,Y,Z
please do this for Items T,U,V,W,X,Y,Z The demand
please do this for Items T,U,V,W,X,Y,Z The demand
please do this for Items T,U,V,W,X,Y,Z The demand
The demand for subassembly S is 100 units in week 7. Each unit of requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S. 1 week to make T, 2 weeks to make U. 2 weeks to make V, 3 weeks to make W. 1 week to make X2 weeks to make y, and 1 week to make Z Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers). Week Lead Time Item 1 4 56 (weeks) S Gross req 100 on hand 20 Net req 80 2 order receipt 80 Order release 80 2 3 7 80 T Gross red On hand 20 Net reg 1 Order receipt Order release The product structure. The time-phased product structure. o a Level 0 w 1 XES T 1 S U IN z 2 V W X(1) Y) 20) Time in weeks Item Item S T U v On-Hand Inventory 20 20 40 20 w Y z On-Hand Inventory 30 25 40 120

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!