Question: please explain all steps Use this information to draw a network diagram. What is the expected duration of this project? Activity Immediate Predecessor Time A
please explain all steps

Use this information to draw a network diagram. What is the expected duration of this project? Activity Immediate Predecessor Time A 5 B 11 C A. B 15 B 21 E B 10 F C, D, E 10 13 G E