Question: Please explain in detail your answer! The following data are average times per order over the last month. Wait time to start production 16.2 days

Please explain in detail your answer!

The following data are average times per order over the last month.

Wait time to start production 16.2 days

Inspection time 1.8 days

Process time 2.7 days

Move time 2.6 days

Queue time 8.2 days

The manufacturing cycle efficiency (MCE) would be closest to:

A. 29%.

B. 82%.

C. 46%.

D. 18%.

E. None of the above