Question: please explain in less than 30 words Question 2 15 points Save Ans The following table shows a data of a project. Answer the following

please explain in less than 30 words please explain in less than 30 words Question 2
Question 2 15 points Save Ans The following table shows a data of a project. Answer the following questions. Duration Activity (weeks) Predecessor A 7 B 5 C 2 , D 3 E 6 c F B DE The project manager found that the activity C had 2 weeks delay, so it was completed in 4 weeks. Please describe one way to meet the original scheduled project delivery date. Just one sentence is fine. No more than 30 words. TTT Arial (1201) TEE 22