Question: Please explain steps in detail im so lost. Something similar is going to be assigned for finals and i dont know how to tackle begin{tabular}{|l|l|l|l|l|}

Please explain steps in detail im so lost. Something similar is goingPlease explain steps in detail im so lost. Something similar is going to be assigned for finals and i dont know how to tackle

to be assigned for finals and i dont know how to tackle\begin{tabular}{|l|l|l|l|l|} \hline Activity & \multicolumn{2}{l}{ Initial Node } & \multicolumn{2}{l|}{ Final Node

\begin{tabular}{|l|l|l|l|l|} \hline Activity & \multicolumn{2}{l}{ Initial Node } & \multicolumn{2}{l|}{ Final Node } \\ \hline A & 1 & 2 & 2 \\ \hline B & 2 & 3 & 3 \\ \hline C & 2 & 4 & 3 \\ \hline D & 2 & 5 & 2 \\ \hline E & 3 & 6 & 4 \\ \hline F & 4 & 6 & 3 \\ \hline G & 5 & 7 & 6 \\ \hline H & 6 & 8 & 2 \\ \hline I & 7 & 8 & 3 \\ \hline J & 8 & 9 & 4 \\ \hline K & 7 & 10 & 5 \\ \hline L & 7 & 11 & 2 \\ \hline M & 10 & 9 & 3 \\ \hline N & 9 & 12 & 3 \\ \hline O & 10 & 13 & 3 \\ \hline P & 11 & 13 & 7 \\ \hline \end{tabular} a) Using the information provided in the table above, draw the AOA network diagram representing the project. Put the node numbers in the circle and draw arrows from node to node, labelling each arrow with the activity letter and estimated time. b) Identify all the paths on the network diagram. Calculate the estimated duration of each path. c) What is the critical path for this project and how long is it? d) What is the shortest possible time it will take the project to complete? Question 2. Using the Network Diagram (from above), fill in the table for each activity. (8 marks) Use the following Table format to summarize your answers. You will need to exoand the table to list all activities. Please use the same order as above: A, B, C, etc. for the rows. NOTE, this table will be on your summary page. However, you must provide all the relevant information for your network diagram in the appendix. You must show each of the values for each activity in on the network diagram. Question 3. Using the information for the small project in the first table above, create the project within MS Project. Once you have created the original project, make the following changes, and answer the applicable questions. ALL these scenarios are to be modeled in MS Project with applicable screen shots for each of the scenarios (original, change a), change b), and change c)) provided in your submission (appendix) as well as the .mpp file for the initial network diagram. (12 Marks) a) The duration for activity I is extended, and the new estimate is I=5 days. What is the impact to the critica path and/or the critical path duration (if any)? b) Revert to the initial state (original network diagram and reset I=3 days). Now, the duration for activity D is extended, and the new estimate is D=4 days. What is the impact to the critical path and/or the critical path duration (if any)? c) Revert to the initial state (original network diagram and reset D=2 days). The project team had a change order that resulted in descoping of activity I from the project. What is the impact to the critical path and/or the critical path duration (if any)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock