Question: please explain the answer tions 5-6 rely on the following data. Major Net Systems has budgeted three hours of direct labor per connector, at a
please explain the answer

tions 5-6 rely on the following data. Major Net Systems has budgeted three hours of direct labor per connector, at a standard cost of $17 per hour. During August, technicians actually worked 189 hours completing 84 connectors. cians $17.80 per hour. All 84 connectors actually produced were sold. MajorNet paid the tech 5. What is MajorNet's direct labor cost variance for Ausgust? a. $67.20 U b. $151.20 U c. $201.60 U d. $919.80 U 6. What is MajorNet's direct labor efficiency variance for August? a. $919.80 F b. $1,071.00 F c. $1,121.40 F d. $3,364.20 F