Question: Please explain thoroughly. For this question, assume partial crashing is allowed; you can crash part of what is max crash time available. 2. Consider a
Please explain thoroughly.
For this question, assume partial crashing is allowed; you can crash part of what is max crash time available.

2. Consider a project having the following seven activities: Normal m Crash Crash Maximum Immediate Time Cost Time Cost Weeks Activity Predecessors (weeks) (5) (weeks) (5) Reduced A none 4 3,000 3 5,000 1 B A 9 5,000 7 3,000 2 c A 4 7,000 4 7,000 0 D B, C 6 6,000 4 8,000 2 E c 8 4,000 6 3,000 2 F D 3 4,000 2 9,000 l G E, F 4 2,000 2 7,000 2 a) What is the expected project completion time? b) What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks