Question: Please explain with figures. 6. Four jobs must be processed on a single machine. The time required to perform each job, the due date, and

Please explain with figures. 6. Four jobs must be processed on a

Please explain with figures.

6. Four jobs must be processed on a single machine. The time required to perform each job, the due date, and the penalty per day the job is late are given in the following table. Use branchand-bound to determine the order of performing the jobs that will minimize the total penalty costs due to delayed jobs