Question: please fast Based on the target schedule, budget cost and pay prices shown below, Find the value of First payment Pay period = 10 working

please fast Based on the target schedule, budgetplease fast
Based on the target schedule, budget cost and pay prices shown below, Find the value of First payment Pay period = 10 working day Retention = 10% up to 5% of contract price. Lum Sum = pay item is paid when activity is completed. Retention is withheld until the end of the project. Select one: O a. 40,500 ob. 57,000 O c. 40,100 O d. 49,000