Question: Please find 5th unit, 6th unit, 7th unit, 8th unit, 9th unit, 10th unit and please show steps, thank you Suad Alwan, the purchasing agent

Please find

5th unit, 6th unit, 7th unit, 8th unit, 9th unit, 10th unit

and please show steps, thank you

Please find 5th unit, 6th unit, 7th unit, 8th unit, 9th unit,

Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the second plane took 20,000 hours to produce. Using an 85% learning curve and a $30-per-hour labor charge, he wants to determine the cost of the six additional planes. Time required for the sixth unit = hours (round your response to the nearest whole number)