Question: please find C,D,E A project and its activities are represented in following table. All times are in weeks. Activity Immediate Predecessor Time A - 4

please find C,D,E
please find C,D,E A project and its activities
A project and its activities are represented in following table. All times are in weeks. Activity Immediate Predecessor Time A - 4 B 3 C A 2 D B 7 CD 4 F B S G 4 Please, fill in this table and use it to answer the questions below: Immediate ES EF LS LF Slack Activity Time Predecessor A 4 B C A D B B C, D F B G E, F 4 Using the table above, what is the latest possible time (in weeks) that C may be started without delaying completion of the project? OA O OB. 8 OC. 10 D. 4 OE. None of the above 3 2 7 4 5