Question: Please find critical path and duration. Then update the schedule based on the bullet points below. Notes: 1. Show all calculations for your solutions. 2.

Please find critical path and duration. ThenPlease find critical path and duration. Then update the schedule based on the bullet points below.

Notes: 1. Show all calculations for your solutions. 2. Use the Engineering Papers. Question 1 (10 points): F 8 B 4 SS5 E FF4 . 10 G 4 5 K 5 8 C 3 H 4 . . . Data Date = 14 Activity A started as planned-took 2 more days. Activity B started on day 5, was completed in its original duration. Activity E began as soon as its predecessor was completed and had a remaining duration of 1 day. Activity C started immediately after Activity A and is 67% completed. No other activities have started. A new Activity L (2 days) follows Activity F and precedes Activity K. The duration of the other activities remains as planned. No other info is available.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!