Question: please give correct Answer i will give you vote according to your response From the data given below calculate the overhead cost variance. Budgeted hours
please give correct Answer i will give you vote according to your response

From the data given below calculate the overhead cost variance. Budgeted hours 25,000 Budgeted output 12,500 Budgeted overheads: Fixed 7500 Variable 5000 12,500 Actual overheads: Fixed 7500 Variable 7500 15,000 Actual output 10,000 units Actual hours 30,000