Question: please give detailed calculations( not in excel) 3. 75. Develop a material requirements plan for end item P and its components, given the tree below.
please give detailed calculations( not in excel)

3. 75. Develop a material requirements plan for end item P and its components, given the tree below. Assume that all lead times are one week, and that lot-for-lot ordering is used except for item F, which is ordered in multiples of 400 units. One hundred units of P should be available at the start of week 4 and at the start of week 8. Beginning inventories are: 20 P, 100 A, and 200 F. Scheduled receipts are: 800 F at the start of week 1. P BG) A(2) (2) DC+ F(2) F(2)