Question: Please help and show work ACCT 21- Week 06: Assignment Exercise A: High-Low Method (6pts) During the year, the highest and lowest levels of activity
ACCT 21- Week 06: Assignment Exercise A: High-Low Method (6pts) During the year, the highest and lowest levels of activity for the Cutler Company direct machine hours and 24,000 direct machine hours, respectively. If maintenance costs were $240,000 at the 34,000-hour level and $200,000 at the 24,000-hour level, what cost might we expect at an operating level of 28,000 direct machine hours? were 34,000
Step by Step Solution
There are 3 Steps involved in it