Question: please help!!!! b) Given the demand, the cycle time for the production of the new train set = ____ seconds c) The theoretical minimum number

please help!!!!
b) Given the demand, the cycle time for the production of the new train set = ____ seconds
c) The theoretical minimum number of workstations= ____(round your response up to the next whole number)
d) Using the long-term operations time rule, the assignment of tasks to the workstations should be (Hint: Number of workstations sequentially in terms of precedence relationships, and combine any applicable tasks)
*were you able to assign all the tasks to the theoretical minimum of the workstations?*
e) The total idle time per cycle for the process= ____ seconds (round response to the nearesr whole number)
f) the efficiency of the assembly with 5 workstations = _____% (round to one decimal place)
g) if one used one workstation instead of 5, the efficiency of the assembly line would be ___% (round to one decimal place
thank you!
please help!!!! b) Given the demand, the cycle
Score: 0 of 3 pts 11 of 11 (10 complete) Problem 9.15 The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4800 units per 40-hour workweek Task A Predecessors - - Performance Time seconds) 24 27 12 15 12 27 A BC DE This is only contains part bad and b) Ghen the demand the cycle time for the production of the new traiestesscode fround your response to one decimal place) Enter you the answer box and then click Check AWE 10 p

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!