Question: Please help - Cash flow table In 2022, Leo construction will work on a residential project that lasts 4 months. The direct costs of the

In 2022, Leo construction will work on a residential project that lasts 4 months. The direct costs of the residential project are shown in the following bar chart. \begin{tabular}{|l|l|l|l|l|l|l|} \hline End of Month & 0 & 1 & 2 & 3 & 4 & 5 \\ \hline MonthlyCost(Direct&IndirectCost) & & & & & & \\ \hline Monthly Billing & & & & & & \\ \hline Monthly Income & & & & & & \\ \hline Retainage & & & & & & \\ \hline Overdraft(beforeinterest) & & & & & & \\ \hline Interest (1\%) & & & & & & \\ \hline Overdraft(deductinterest) & & & & & & \\ \hline Overdraft(addincome) & & & & & & \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts