Question: please help Crane Corp. has collected the following data concerning its maintenance costs for the past 6 months. Total Cost July August September October November

Crane Corp. has collected the following data concerning its maintenance costs for the past 6 months. Total Cost July August September October November December Units Produced 19.900 35,552 39.996 24.442 44.440 42.218 $44.732 53,328 61.105 46.388 82.769 68.882 X Your answer is incorrect. Compute the variable cost per unit using the high-low method. (Round answer to 2 decimal places eg. 2.25.). Variable cost per unit a