Question: please help fast 24 Question 24 Consider the following project: Predecessors Task ID 2 000 N 8 9 10 11 12 Duration (Days) 70 30

please help fast 24
please help fast 24 Question 24 Consider the
Question 24 Consider the following project: Predecessors Task ID 2 000 N 8 9 10 11 12 Duration (Days) 70 30 120 120 120 120 150 115 130 90 30 120 75 30 85 165 90 90 20 2 3 2 5 3,6 3,6 3,6 7,9 7.9 7,9 7,9 10 14 13 14 15 6 16 16 17 16 18 19 20 17,18 8,11,13,15,19 If task 14 takes 15 days longer to complete the duration of the project would Increase by 15 days Cannot say with information provided Increase by 10 days Stay the same