Question: *Please help - I was able to complete part A, but need help answering the rest of the questions based on the table and part
*Please help - I was able to complete part A, but need help answering the rest of the questions based on the table and part A below.*
Projects A and B, of equal risk, are alternatives for expanding Rosa Company's capacity. The firm's cost of capital is 13%. The cash flows for each project are shown in the following table.
| Project A | Project B | |||||
| -$130,000.00 | -$85,000.00 | |||||
| Initial Investment (CF0) | ||||||
| Year (t) | Cash Inflows (CFt) | |||||
| 1 | $25,000 | $40,000 | ||||
| 2 | $35,000 | $35,000 | ||||
| 3 | $45,000 | $30,000 | ||||
| 4 | $50,000 | $10,000 | ||||
| 5 | $55,000 | $5,000 | ||||
| Question A | ||
| Calculate each project's payback period |
| Project A | Project B | ||||||||||
| Year | Cash Flow Stream | Cumulative Cash Flow | Year | Cash Flow Stream | Cumulative Cash Flow | ||||||
| 0 | -130,000 | -130,000 | 0 | -85,000 | -85,000 | ||||||
| 1 | 25,000 | -105,000 | 1 | 40,000 | -45,000 | ||||||
| 2 | 35,000 | -70,000 | 2 | 35,000 | -10,000 | ||||||
| 3 | 45,000 | -25,000 | 3 | 30,000 | 20,000 | ||||||
| 4 | 50,000 | 25,000 | 4 | 10,000 | 30,000 | ||||||
| 5 | 55,000 | 80,000 | 5 | 5,000 | 35,000 | ||||||
| Total | 80,000 | Total | 35,000 | ||||||||
| Payback period (PBP) = Numerical Value of the last year with negative cash flow + (Absolute value of that negative cash flow / Total cash flows of the next year) | |||||||||||
| Project A = 3+(25,000/50,000) | Project B = 2+(10,000/30,000) | ||||||||||
| 3.5 | 2.33 | ||||||||||
| Years is the payback period for Project A | Years is the payback period for Project B | ||||||||||
| Question B | ||
| If the return on the market portfolio increased by 12%, what change would you expect in return for each stock? |
| Question C | ||
| If the return on the market portfolio decreased by 5%, what change would you expect in return for each stock? |
| Question D | ||
| If you believed the stock market was getting ready to experience a significant decline, which stock would you probably add to your portfolio? Why? |
| Question E | ||
| If you anticipated a major stock market rally, which stock would you add to your portfolio? Why? |