Question: please help! Immediate Predecessor(s) Activity Time Activity 5 un A 8 00 B 6 A D 2 B, C E C, D 00 8 F

please help!
please help! Immediate Predecessor(s) Activity
please help! Immediate Predecessor(s) Activity
Immediate Predecessor(s) Activity Time Activity 5 un A 8 00 B 6 A D 2 B, C E C, D 00 8 F TI E 9 G G B 11 H H F, G 5 b. Identify the critical path. The critical path is Select C. What is the project completion time? Round your answer to the nearest whole number weeks