Question: Please help! I've posted this question before but the answers I got were incorrect. The answers in the blue boxes are correct. White boxes are
Please help! I've posted this question before but the answers I got were incorrect. The answers in the blue boxes are correct. White boxes are incorrect answers.
Can you please help me find the correct answers for the ending inventory, net requirement, planned receipts and planned orders? (Planned orders doesn't show up until everything else is filled out)

Consider the following master schedule record. Now suppose the lead time for item A2 is three weeks rather than one week. Based on this information, can the company support the current gross requirements for the A2? What are the implications of having reliable supplier and manufacturing lead times in an MRP environment? Click the icon to view the MRP record. Calculate the material requirements plan (enter your responses as whole numbers and include a minus sign if necessary). 3 5 6 Week ***A2*** LT(weeks) = 3 1 0 4 100 350 450 100 2 300 40 0 50 0 0 0 0 Gross requirements Scheduled receipts Projected ending inventory: 50 Net requirements Planned receipts 0 210 350 100 450 100 Min. order = 1 0 210 350 100 450 100
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock