Question: please help last answer was wrong Use the following MRP record and your calculations to answer the following question(s). The component has an order quantity

please help last answer was wrong

Use the following MRP record and your calculations to answer the following question(s). The component has an order quantity of 100 (EOQ=100), and a lead time of one period. Complete the following MRP record.

Period

1

2

3

4

Gross Requirements

25

80

50

80

Scheduled Receipts

100

Projected on-hand 30

Net Requirements

Planned-order Receipts

Planned-order Releases

What is the projected available inventory in period #4?

How much is the inventory costs if ordering cost is $40 per order, and carrying cost is $3 per unit per week?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!