Question: please help. make sure to answer in dollars and not in thousands of dollars. Clarita Contracting bullds roads, tunnels, bridges, and other transportation infrastructure. The

Clarita Contracting bullds roads, tunnels, bridges, and other transportation infrastructure. The following are the budgeted costs and time (months) to a given stage of completion for a project to upgrade a bridge to current standards. The project was originally estimated to take 25 months to complete. Also presented are the actual results through the first 11 months of the project. Required: a. At this time, what is the current cost over- (under-) run on the project? Note: Enter your answer in dollars and not in thousands of dollars. b. At this time, by how far ahead or behind schedule is the project in terms of percentage of completion