Question: Please help me answer A , B and C:Consider the activities for Project Able, and their normal and crash times and costs as shown in
Please help me answer A B and C:Consider the activities for Project Able, and their normal and crash times and costs as shown in the table below. Note that Crash Time is the fastest that the activity can be done and Crash Cost
is the total cost to do the activity at its fastest. Assume that crash costs are linear.
Note: Activity U cannot be crashed.
Suppose that based on the precedence relationships not shown here the project has one critical path at the normal times
The critical path is: SVXY
a Which activity or activities should be crashed in order to reduce the expected project completion time by one period, and what will it cost to do so
The activityactivities to crash: firstcrash
The cost to do this crash: firstcost dollars.
b Suppose that after the crash you just did, the same path is critical and no new critical path has emerged. Which activity or activities should be crashed now, in order to reduce the expected
project completion time by one more period, and what will it cost to do this?
The activityactivities to crash now: nextcrash
The cost to do this crash: nextcost dollars.
c After your crash in part b what is the expected project completion time? time days.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock